Build dates trans am cars

Started by cudamadd, September 27, 2020, 10:09:34 PM

Previous topic Next topic

0 Members and 2 Guests are viewing this topic.

cudamadd

AAR  and T/A  hi what were the time frame of the building of the trans am cars . So how long were they build for ? Start to finish from the factory ?  Thank you again for your knowledge cheers Aussie  :australia:

6bblgt

not counting any "pilot" TRANS AM car builds
- the A53 cars were "SCHEDULED" for roughly 6 weeks 3/10 to 4/17
- the A53 cars were actually built "In Plant/In Process" for roughly 8 weeks 3/6 to 5/4


cudamadd



ply64post

Quote from: 6bblgt on September 28, 2020, 12:28:12 AM
not counting any "pilot" TRANS AM car builds
- the A53 cars were "SCHEDULED" for roughly 6 weeks 3/10 to 4/17
- the A53 cars were actually built "In Plant/In Process" for roughly 8 weeks 3/6 to 5/4

6bblgt
Saw a TA fender tag that was a production date of 216 and vin started with 296 or 286 is this possible?  :thinking:

6bblgt

it appears assigned VINs:
0B286xxx are all Valiants - Scheduled late March
0B296xxx includes AARs & T/As  - Scheduled early April

ply64post

Quote from: 6bblgt on September 28, 2020, 12:26:46 PM
it appears assigned VINs:
0B286xxx are all Valiants - Scheduled late March
0B296xxx includes AARs & T/As  - Scheduled early April

I looked at the tag again the vin is 296 but the date sure looks like 216. The date caught my attention that is why I asked.               
                                                                           A mistake?

6bblgt

can you post a picture of the tag?  :takealook:


ply64post

Quote from: 6bblgt on September 28, 2020, 01:02:22 PM
can you post a picture of the tag?  :takealook:

Here is a copy.


6bblgt

that tag is FAKE with numerous errors - I would "ASSUME" the car has NO other documentation  :dunno:

ply64post


No that is all there was and 3 or 4 pictures.